Sundargarh · 2024
Conveyor gallery rebuild
Replacement of corroded gallery members during shutdown
- Client
- A coal handling plant, Sundargarh
- Location
- Sundargarh
- Service
- Mechanical installation & plant maintenance
- Quantity
- 22 tonnes replaced
- Duration
- 96-hour shutdown
- Year
- 2024
The job
Corroded trestle and gallery members had to be replaced inside a fixed 96-hour shutdown.
What we did
Every replacement member was pre-fabricated from site measurements before the shutdown, then cut out and replaced in sequence with temporary supports and two shifts.
Result
Finished in 81 hours; the plant restarted 15 hours early.