Sundargarh · 2024

Conveyor gallery rebuild

Replacement of corroded gallery members during shutdown

Client
A coal handling plant, Sundargarh
Location
Sundargarh
Service
Mechanical installation & plant maintenance
Quantity
22 tonnes replaced
Duration
96-hour shutdown
Year
2024

The job

Corroded trestle and gallery members had to be replaced inside a fixed 96-hour shutdown.

What we did

Every replacement member was pre-fabricated from site measurements before the shutdown, then cut out and replaced in sequence with temporary supports and two shifts.

Result

Finished in 81 hours; the plant restarted 15 hours early.

Industry: Steel, power and mining

Conveyor gallery on trestles

Elevation of the structure

A circular steel frame structure against a dark sky
A worker in gloves grinding a steel bar
Sparks flying from an angle grinder cutting steel
Looking up at a steel lattice tower