Bargarh · 2023

Raw water pipeline, 2.4 km HDPE

Laying, butt-fusion jointing and hydro testing

Client
A water supply scheme, Bargarh
Location
Bargarh
Service
Piping works
Quantity
2,400 m of 315 mm HDPE
Duration
9 weeks
Year
2023

The job

A raw water line from the intake to the treatment plant, laid before the monsoon.

What we did

We laid and butt-fused the line in 200 m strings, built valve chambers and thrust blocks, and hydro-tested each section.

Result

Commissioned two weeks before the monsoon; all test sections passed first time.

Industry: Water supply and irrigation

Pipeline on supports to the tank

Elevation of the structure

Insulated process piping and valves in an industrial plant
A welder in safety glasses welding a large steel pipe
Site engineers in helmets and vests on a construction site
Reinforcement steel tied in a grid before concreting

Start a project

Discuss a similar project.

Tell us the scope and location. We visit the site and send a written quotation within 2 working days.

Call WhatsApp Quote