Jharsuguda · 2025
Coil storage shed, 40 × 20 m
Portal-frame shed with 20 m clear span
- Client
- An aluminium smelter, Jharsuguda
- Location
- Jharsuguda
- Service
- Structural steel fabrication & erection
- Quantity
- 45 tonnes structural steel
- Duration
- 6 weeks
- Year
- 2025
The job
The plant needed covered storage for finished coils beside a working yard, without stopping its traffic.
What we did
We fabricated trusses, columns and purlins in our workshop, delivered them in sequence and erected the frame bay by bay with a 14-tonne hydra, keeping one yard lane open throughout.
Result
Handed over in 41 days with zero lost-time incidents and a joint inspection signed on the first walk.