Skip to content

Angul · 2025

Three-tier pipe rack, 60 m

Pipe rack with a cable-tray tier, inside a running plant

Client
A captive power plant, Angul
Location
Angul
Service
Platforms, pipe racks & staircases
Quantity
38 tonnes, 9 frames
Duration
5 weeks
Year
2025

The job

A new utility line had to cross the plant between two buildings with no shutdown.

What we did

We set out the rack around existing foundations, fabricated frames short enough for plant roads, and erected them during permitted hours under hot-work permits.

Result

Completed in 33 days, 18,600 safe man-hours, no permit deviations.

Industry: Steel, power and mining

Three tiers, 6 m bays

Elevation of the structure

A steel pipe rack carrying large pipes across an industrial plant
Insulated process piping and valves in an industrial plant
A welder in safety glasses welding a large steel pipe
A worker in high-visibility gear working at height

Start a project

Discuss a similar project.

Tell us the scope and location. We visit the site and send a written quotation within 2 working days.

Call WhatsApp Quote