Angul · 2025
Three-tier pipe rack, 60 m
Pipe rack with a cable-tray tier, inside a running plant
- Client
- A captive power plant, Angul
- Location
- Angul
- Service
- Platforms, pipe racks & staircases
- Quantity
- 38 tonnes, 9 frames
- Duration
- 5 weeks
- Year
- 2025
The job
A new utility line had to cross the plant between two buildings with no shutdown.
What we did
We set out the rack around existing foundations, fabricated frames short enough for plant roads, and erected them during permitted hours under hot-work permits.
Result
Completed in 33 days, 18,600 safe man-hours, no permit deviations.